Slipform

Slipform Technique of concrete pouring (Part-II)

(Contd. from Part-I)…..

Some of the salient components of a typical slipform equipment are:

* Several units of steel forms of suitable size. The number of forms is a function of the bottom diameter of the structure. So, if the length of each form is, say 2.5m, then the total number of forms required comes to bottom circumference divided by 2.5m. Height of forms can normally be 1m. Dimensions may vary also, but forms with abovementioned dimensions are quite suitable for a tall structure.

* An inside ring that holds together the whole slipform assembly. After arriving at the number of the slipform units, the inside rimg is fabricated accordingly.

* Hydraulic jacks of suitable diameter. 6 ton jacks can be quite workable for a reasonably tall & big structure.

* Trusses to bear the entire load of the slipform structure. Several steel trusses are required, the number of which depends on the size of the slipform structure or the design of the trusses etc. Six medium sized trusses could be good enough for a reasonably big chimney, tower or a silo.

* A concrete lifting arrangement on top of the platform supported by the trusses, normally provided at the centre of the structure.

* One winch just outside the structure to lift reinforcement steel.

* The slipform assembly may have three decks for different purposes. The top deck is used for concrete pouring. Intermediate one is for fixing re-bars. It can also be used for checking various dimensions of the structure at required elevations in order to maintain correct profile of the same. The lowermost deck is normally used for finishing work.

* A plumb arrangment in order to keep checking the verticality of the structure. The frictional forces between the forms & concrete plays bit of a spoilsport due to which the whole assembly may tend to loose verticality that is required to be maintained. Hence, the same needs to be checked & ascertained using a plumb or similar aid at regular intervals (say, half a meter) of heights and necessary corrections are done promptly using the jacks. Normally, water levels are attached to the yokes to ensure uniform lifting of the entire slipform unit.

* Suitable lifting arrangement is provided usually just outside the structure for smooth movement of workers, engineers etc.

* Proper curing facility: It can be ensured by ring shaped sprinkler pipes along the lowermost deck.

* Efficient communication system between top of the structure & ground staff is vital. A good telephone system serves the purpose well.

* An excellent safety arrangement is a must for these kinds of work. Apart from the usual helmets, safety belts & shoes etc., a strong safety net or a similar aid must be provided around the circumference of the lowermost deck.

Advertisements

About clazcons

B. Tech. (Civil Engineering)

Discussion

No comments yet.

Please leave Comments here.

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: